1. Completed move of Triennial Committee functions to front office in Central Station. TM office is now in back office. Front office to be manned by volunteers during meets and work weeks. This is a hint: We need volunteers to fill this important function during meets and work weeks - end of hint!
2. Construction work on new weed sprayer.
3. Contract with 7idea Productions for videographer for Triennial (dvd's).
4. Contract with Waste Management (trash).
5. Contract with Jefferson State Pumping (porta potties).
6. Constructed / installed security devices for Train Mountain.
7. Clean up of Backshop including rearrangement of equipment storage.
8. 15 portable riding seats, cutout, constructed, painted, installed (5 each 3 seat cars).
9. Break in the weather - raking and pick up started (1/2 mile complete, 34 1/2 miles to go).
10. Layout of Commemorative Program almost complete (need photo ready ad artwork from vendors).
11. Ongoing signal maintenance.
12. Painted lots and lots of green blocks.

Above work completed by volunteers (week ending 4-6-2012)
Boyd, Bert, Charlie, Tom, Dennis, Russ, Aaron, John Cooper, Barbara, Dana and others